Quick Take: Chongjin Destroyer Recovery Efforts Continue

On May 21, North Korea attempted to launch the second destroyer in its new Choe Hyon Class at Chongjin Port. As reported in North Korean State media, the side-launch resulted in a “serious accident,” due to “inexperienced command and operational carelessness”. Specifically, the stern hit the water first, leaving the ship’s bow hung up on the launch way. Further exacerbating the incident were openings in the unfinished deck of the vessel which allowed water to pour into its interior compartments as the ship laid on its side in the water. Kim Jong Un set a June deadline for the restoration of the vessel, and commercial satellite imagery indicates that swift efforts to remove the ship from the water are underway.

On imagery from May 29, over 30 probable barrage balloons have been positioned alongside the vessel to help lift and/or keep the vessel afloat. Another five were on the quay. In addition, cables are attached to to the ship, tethering it to stabilize its position.

Figure 1. Imagery from May 29 reveals barrage balloons are being used to keep the overturned vessel afloat, while nearby support vessels remove water from the ship. Image Pleiades NEO © Airbus DS 2025. For media options, please contact [email protected].

Two nearby support vessels are pumping water out of the ship, in efforts to float the destroyer and remove its bow from the launch mechanism. On land, dollies have been pulled back to the building ways. These dollies had been used to move the ship to the launch mechanism, where levers were inserted to raise the vessel for the actual launch.

In addition, the channel providing sole access to the inner harbor is being dredged, an action necessary due to built-up silt. This area must be cleared to allow for the eventual departure of the new destroyer.

Figrue 2. Imagery from May 29 reveals dredging is occuring at the port’s accessway. This work will be necessary for when the vessel needs to exit the port. Image Pleiades NEO © Airbus DS 2025. For media options, please contact [email protected].

These efforts indicate progress from immediately after the incident. Imagery from May 22 indicated the blue tarp was placed over the majority of the vessel, particularly over the forward half of the ship, concealing remnants of the launch mechanism that did not separate during the launch attempt and likely to help obstruct analysis of the cause of the failure and severity of the damage to the vessel.

Several cranes were tethered to the ship at that time, likely restraining it from slipping into the water and flooding completely.

Figure 3. Imagery from the day after the launch attempt shows cranes and tethers holding up the vessel. Image Pleiades NEO © Airbus DS 2025. For media options, please contact [email protected].

At the building ways, new hull plates are visible, although material is covering other portions of the construction activity.

Figure 4. Activity is ongioing at the building way area, where the previous destroyer was built. Hull plates are visible, but other materials are covered. Image Pleiades NEO © Airbus DS 2025. For media options, please contact [email protected].
Stay informed about our latest
news, publications, & uploads:
I'm interested in...
38 North: News and Analysis on North Korea